Proposition A
-
Proposition A – Constructing and Upgrading School Buildings $156.8M
Numbers are rounded and based on industry standards for educational facilities by preferred district architect, Corgan. Due to rising construction costs, the cost escalations are based on a tentative construction timeline.
- High School –
- NEW Career & Technical Education (CTE) Addition - $25,400,000
- Program sq. ft. 50,000 = $17,250,000
- Covered walkway to connect to HS = $75,000
- Development costs (permit, HVAC tests, engineering, tech equipment, FF&E, and fees) = $4,100,000
- Escalation projected costs = $3,900,000
- Campus Practice Gym Addition & Renovations - $14,100,000
- New Practice Gym and HS space = $6,000,000
- Replace seating in Competition Gym = $200,000
- Replace entire HS flooring = $2,750,000
- Development Costs = $1,700,000
- Escalation projected costs = $2,000,000
- NEW Career & Technical Education (CTE) Addition - $25,400,000
- Middle School –
- NEW Middle School on the west side of town (land already acquired) - $85,100,000
- Program sq. ft. 170,000 = $56,950,000
- Development costs (permit, HVAC tests, engineering, tech equipment, FF&E, and fees) = $11,955,000
- Escalation projected costs = $16,100,000 (3 years project)
- Safety modifications to existing middle school
- NEW Middle School on the west side of town (land already acquired) - $85,100,000
- Elementary Schools –
- Addition to Wooden ES (8 classrooms, new cafeteria) - $13,500,000
- New cafeteria and kitchen = $4,800,000
- Storm shelter = $1,000,000
- Interior renovations for 8 classrooms = $2,000,000
- Replace all exterior doors = $125,000
- Development costs = $1,900,000
- Escalation projected costs = $3,250,000
- Addition to Eastridge ES (8 classrooms, new cafeteria) - $13,500,000
- New cafeteria and kitchen plus equipment = $4,800,000
- Storm shelter = $1,000,000
- Interior renovations for 8 classrooms = $2,000,000
- Replace all exterior doors = $125,000
- Development costs = $1,900,000
- Escalation projected costs = $3,250,000
- Addition to Wooden ES (8 classrooms, new cafeteria) - $13,500,000
- District-Wide Maintenance Items
- Playgrounds (All 5 elementary schools) - $1,500,00
- Shields = $100,000
- EES, RPS, HAW, ROE = $250,000 each
- LHLC = $25,000
- Development costs = 178,250
- Escalation projected costs = $155,000
- Energy Management System Upgrades
- EES, HAW, ROMS, Stadium = built into renovation costs
- ROHS, RPS, ROE, DTS, LHLC, ESC = $1,600,000
- Electrical and systems upgrades = $200,000
- Development costs = $245,400
- Escalation projected costs = $275,000
- Playgrounds (All 5 elementary schools) - $1,500,00
- High School –
Proposition B
-
Proposition B – Renovating Goodloe Stadium $45.0M
- Rebuild Stadium to Current Codes
- Additional parking and Seating
- 8 Lane Track (UIL) and LED Field Lighting
- New Restrooms, Locker Rooms, and Concessions
- Cost Breakdown
- Home side 1,000 new parking spots and re-stripe existing for handicap, accessibility = $5,325,00
- Home seating/stands = $2,270,000
- Press box = $3,125,000
- Under current press box concessions and restrooms, paving, transformer = $1,900,000
- Visitor side parking and accessibility = $2,750,000
- Visitor seating/stands - $950,000
- South endzone - new multipurpose concessions, locker rooms, restrooms = $13,000,000
- Sidewalks and accessibility = $375,000
- Bus, official parking and connection = $660,000
- North endzone
- Demolition, leveling, transformer moved = $350,000
- New north plaza = $250,000
- Scoreboard = $1,000,000
- Widening drive between stadium and MS = $775,000
- LED Lighting = $450,000
- Track upgrades to 8 lanes and resurfaced = $600,000
- Development costs = $6,200,00
- Escalation projected costs = $5,400,000
- Home side 1,000 new parking spots and re-stripe existing for handicap, accessibility = $5,325,00
Proposition C
-
Proposition C – Upgrading Recreation Facilities, High School $9.3M
- NEW JV Stadium – Track and Turf Field $6.0M
- 8 lane track, turf field, bleachers, LED lighting and fencing = $3,750,000
- Parking and road = $615,000
- Retention modifications, utility/system upgrades = $550,000
- Development costs = $570,000
- Escalation projected costs = $590,000
- Baseball/Softball Artificial Turf at Existing Fields $3.0M
- Baseball turf = $1,600,000
- Softball turf = $675,000
- Subsurface, utility modifications = $200,000
- Development costs = $170,000
- Escalation projected costs = $356,000
- Resurface Existing Tennis Courts $300K
- Resurfacing tennis courts = $261,000
- Development costs = $23,000
- Escalation projected costs = $31,000
- NEW JV Stadium – Track and Turf Field $6.0M
Proposition D
-
Proposition D – Constructing a New Transportation Facility $19.0M
- NEW Facility and Parking
- Three bay shop and support = $3,300,00
- Admin. and driver's area = $2,625,000
- Driver dedicated parking area = $576,000
- Bus parking = $5,000,000
- Fuel Station = $450,000
- Security Fence = $125,000
- Development costs = $2,700,000
- Escalation projected costs = $4,750,000
- NEW Facility and Parking